Villa A1 completed
Glass facade, timber eave, the pool filled; the villa was furnished by 16 January.
Stage: Completed
- Started
- 18 Apr 2024
- Completed
- 13 Jan 2025
- Built by
- Number Twelve
- Dated records · photos
- 11 · 8

Chapter 03Nine months
Villa A1 went from piles in May 2024 to a finished, furnished house in January 2025. Here is every dated record with the site photos.
01The profile
Glass facade, timber eave, the pool filled; the villa was furnished by 16 January.
Stage: Completed
02Site records
Built by Number Twelve, the construction company of The Attitude Club, with a weekly report to the project team.
The contractor's programme for villa A1 starts on 18 April 2024.
Stage: Start
The piling rig drives precast piles on the cleared plot.
Stage: Piles
Ground beams cast and the pool shell formed in one go with the house.
Stage: Foundations
The concrete frame rises; the site board goes up.
Stage: Frame
Weekly report no. 16 of Number Twelve, the group's construction company: brick walls up, the roof frame going on. The photo is from 31 August.
Stage: Structure
The roof closes over the villa.
Stage: Roof
Walls plastered, aluminium window frames in, terrace slabs poured.
Stage: Envelope
The roofed villa behind its boundary wall while the finishing crews work inside.
Stage: Finishing
Timber ceilings installed, the kitchen being fitted.
Stage: Fit-out
Glass facade, timber eave, the pool filled; the villa was furnished by 16 January.
Stage: Completed
The finished A1 was shot by professional photographers and from the air. The other seven plots were cleared; their villas are not yet started.
Stage: Show villa ready to walk
Your villa's build time and the payment stages tied to it are written into your contract.
→Next step
We send the contract timeline and the stage payments for the plot you choose.
MMNNine months
MMNSurvey request
Name a plot code or just the number of bedrooms. We reply with the free plots, the price and the viewing times.